200.0 MW
127.4 MW
The request exceeds at least one screened connected N-1 thermal limit.
Candidate: load at bus 3 · request 150.0 MW · Q 0.0 Mvar
Conditional connection actions
| Outage | Maximum candidate MW | Required curtailment | Binding element |
|---|---|---|---|
| row 1: 1–2 | 128.0 MW | 22.0 MW | row 8: 1–3 |
| row 2: 2–3 | 146.9 MW | 3.1 MW | row 8: 1–3 |
| row 5: 5–1 | 146.6 MW | 3.4 MW | row 8: 1–3 |
| row 8: 1–3 | 127.4 MW | 22.6 MW | row 2: 2–3 |
Smallest modeled rating-relief set
| Element | Total +MVA | Request-attributable +MVA | Driving outage |
|---|---|---|---|
| row 2: 2–3 | +13.3 MVA | +13.3 MVA | row 8: 1–3 |
| row 8: 1–3 | +12.9 MVA | +12.9 MVA | row 1: 1–2 |
Better connection points
| Bus | N-1 thermal headroom | Decision |
|---|---|---|
| 1 | 200.0 MW | GO |
| 2 | 135.1 MW | CONSTRAINED |
| 5 | 131.8 MW | CONSTRAINED |
Traceability, scope and assumptions
Analysis ID: 31a5ebfd762315fafd1b
Engine: MWClear 0.6.0
Engine source SHA-256: 22051e119f9ccb721d851d8f965d521e28cbe34d0bdef349ccb18a5524e2d1b9
Input SHA-256: 08a8f69e3ce86cf3fc1b69d1e369bf685d384fe3733b7c219725911659b78b91
Rating policy: RATE_A is applied to both N-0 and connected N-1 states
Selected monitored/outage rows: 8 / 8
Recorded model omissions: None recorded
Fast DC/PTDF/LODF screen using RATE_A and generator limits. Recorded preventive-dispatch policy: generator-bounds-constrained preventive dispatch minimizing the worst normal and connected N-1 branch utilization, followed by a strictly convex least-squares tie-break anchored to supplied generator PG. Candidate transfers use bounded proportional generator participation. Redispatch remains idealized within PMIN/PMAX: ramp limits, reserves, costs, and area interchange constraints are not modeled. It also excludes dynamics, protection, constructability, cost, schedule, outage probability, and 0 selected islanding outages. The optional AC badge covers only the snapshots explicitly listed in result.json. “+MVA” is a mathematical rating delta, not a construction design or price. Use this to choose where to study next, not as an interconnection approval.